Client: Shetland Islands Council

Date: 2012-2015 inclusive. Contract previously held since 2000 (3 terms of 3 years with 1 year extension on each)

Value: Not Stated

Work Description: 

Malakoff Limited are the main contractor for the SVT Jetty Maintenance works. Work scope includes; electrical and mechanical maintenance, fabrication and installation of new and replacement metalwork, maintenance of Jetty structures.

All work is undertaken within the SVT safe system of work-under permit authority and managed from the Malakoff facility at Sella Ness, which comprises of offices, secure laydown area compound and berthing for our fleet of marine vessels including 3no 16m work boat and 2no fully equipped 8m safety boats

The following are case studies for specific programmed works completed in 2013 as part of the contract works:

 

Project Title:

Pipework and related metal work replacement on Jetty 2 (SVT Jetty Contract)

Description:

The existing pipework underneath Jetty 2 was replaced with GRP pipework.

Work Scope:

The work scope included:

  • Removal and disposal of existing steel pipework and supports
  • Fabrication of Stainless Steel pipe support saddles to support replacement pipework
  • In house fabrication of threaded nylon sockets to accept pipe support fixings
  • Installation of pipe support saddles by core boring fixing points with a hydraulic core drill and fixing nylon sockets into position using marine epoxy grout
  • Management of specialist subcontractor appointed to carry out GRP pipework installation.
  • Supply of support resources and plant to subcontractor during pipework installation.

Extensive hydro-demolition was carried out to the concrete surrounding the existing pipework to allow suitable access to install the new GRP pipework. All Sub-Contractor resources and logistics were managed by Malakoff Limited. 

 

Project Title:

Fabrication of Access Platforms on Jetty 3 – Mooring Dolphins (SVT Jetty Contract)

Description:

Fabrication and installation of Access walkway and platform to allow Malakoff operatives to carry out blasting and painting works on the steel piles and to gain access for concrete repairs to the soffits of the Dolphins on MD1 and MD7.

 

Project Title:

Blasting and painting of Jetties 1, 3 and 4 Main Walkway Steelwork

Description:

 Blasting and painting of walkway steelwork structure using Trolley Beam with access cradle platform attached.

 

Project Title:

 Replacement of Jetty Capstans and Winches on all 4 Jetties (SVT Jetty Contract)

Description:

 Replacement works carried out by Malakoff COMPEX electricians, working around tanker movements to replace Jetty machinery on all 4 Jetties, including isolation, removal, disposal, installation and electrical testing.

 

Project Title:

 Maintenance of Berthing Lights on all 4 Jetties (SVT Jetty Contract)

Description:

 Repaired or replaced exterior and interior fixtures and fittings across Jetties, followed by electrical testing of fittings and circuits.

New Jetty 2 Slops GRP Pipework Zoom

New Jetty 2 Slops GRP Pipework

Landing Area for Jetty 2 Slops pipework work Zoom

Landing Area for Jetty 2 Slops pipework work

Installation of Access Platforms underneath Jetty 2 Zoom

Installation of Access Platforms underneath Jetty 2

Installation of Access Platforms underneath Jetty 2 Zoom

Installation of Access Platforms underneath Jetty 2

Core Boring of holes for pipework supports Zoom

Core Boring of holes for pipework supports

Mobilisation on walkway 4 Blasting project Zoom

Mobilisation on walkway 4 Blasting project

Brenda working on Mooring Dolphin Access Platforms Zoom